Activity Based Costing Question No.5 (with answer)

A company manufactures two products, X and Y, using the same equipment and similar processes. Data for the production of these items in one period is shown below:

Data:

Quantity produced per period

X

Y

Material cost per unit

20,000

10,000

Direct labor hours per unit

$20

Machine hours [...]

December 5, 2009  Tags: Activity based costing questions, Activity based costing questions and answers  Posted in: Activity-Based Costing  No Comments

Activity Based System Question No 4 (with answer)

Question:
1(a) For below table, please fill up the following values
(i)В В  Overhead per cost driver unit
(ii)В  Total Overhead per product per activity
(iii) Cost per item

Activity

Total Overheads

Total Cost driver units

Overhead per cost driver unit

Cost driver [...]

December 4, 2009  Tags: Activity based costing questions, Activity based costing questions and answers  Posted in: Activity-Based Costing  No Comments

Answer To Management Accounting Question No:ABC2 on Activity Based Costing

Refer to Accounting Test Question No.ABC2
 

(a) Computation of the activity based overheads
Step 1: Compute cost per unit of cost driver
= Cost pool / cost driver volume

Activity

Cost pool (a)

Cost driver volume/yr (b)

Cost/unit of cost driver (a)/(b)

Purchasing

$75,000

1,500

$50/purchase order

Setting

$112,000

2,800

$40/batch

Materials handling

96,000

8,000

$12/movement

Inspection

$70,000

2,800

$25/batch

Machining

$150,000

50,000

$3/machine hour

Step 2: Compute the volume of cost drivers consumed by Product XX

Purchase orders (given) =25

Batches=15,000/100=150

Materials movement=150 batches [...]

November 23, 2007  Tags: Activity based costing questions and answers  Posted in: Activity-Based Costing  One Comment